CaseDetails
Summary
Case ID
14724
Case Status
Proposal Description
Kudusberg Wind Farm (Pty) Ltd (hereafter referred to as “Kudusberg Wind Farm”) was issued with an Environmental Authorisation (EA) for the proposed construction of the 325MW Kudusberg Wind Energy Facility (WEF) and associated infrastructure, between Matjiesfontein and Sutherland in the Western and Northern Cape Provinces. The EA was granted on 25 March 2019 (DEFF Reference No.: 14/12/16/3/3/1/1976, and subsequently amended on 04 April 2019 to correct a minor naming error (14/12/16/3/3/1/1976/AM1).
Kudusberg Wind Farm is now proposing to submit a Part 2 EA Amendment Application to split the authorised Kudusberg WEF (14/12/16/3/3/1/1976/AM1) into two (2) separate smaller WEF projects, namely the Kudusberg WEF and Oya WEF, which result in a number of technical and administrative changes. The split is being proposed to allow the projects to be suitable for numerous opportunities such as either the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP), Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP), other government run procurement programmes that may arise or for sale to private entities, if enabled and/or required in the drive for energy security in South Africa.
Following the split, the northern section of the authorised WEF will become the Oya WEF, while the southern section of the authorised WEF will remain known as the Kudusberg WEF (authorised under 14/12/16/3/3/1/1976/AM1). In this report, the final layout for the Oya WEF has been subject to a detailed specialist walk-through and on site micro-siting as per condition 29 of the Kudusberg EA. Furthermore, the approved EMPr authorised as part of the Kudusberg EA is being amended to each WEF and to incorporate the final layout for the Oya WEF, management plans and the walk-throughs.
Linked to Kudusberg WEF Case Application: 13208
Kudusberg Wind Farm is now proposing to submit a Part 2 EA Amendment Application to split the authorised Kudusberg WEF (14/12/16/3/3/1/1976/AM1) into two (2) separate smaller WEF projects, namely the Kudusberg WEF and Oya WEF, which result in a number of technical and administrative changes. The split is being proposed to allow the projects to be suitable for numerous opportunities such as either the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP), Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP), other government run procurement programmes that may arise or for sale to private entities, if enabled and/or required in the drive for energy security in South Africa.
Following the split, the northern section of the authorised WEF will become the Oya WEF, while the southern section of the authorised WEF will remain known as the Kudusberg WEF (authorised under 14/12/16/3/3/1/1976/AM1). In this report, the final layout for the Oya WEF has been subject to a detailed specialist walk-through and on site micro-siting as per condition 29 of the Kudusberg EA. Furthermore, the approved EMPr authorised as part of the Kudusberg EA is being amended to each WEF and to incorporate the final layout for the Oya WEF, management plans and the walk-throughs.
Linked to Kudusberg WEF Case Application: 13208
Post date
16/11/2020 - 10:55
Last modified
10/07/2024 - 16:13
Reports
AIA Phase 1 | AIA - Kudusberg | Katie Smuts | download | |
BE & CL Phase 1 | CLA - Kudusberg | Emmylou Rabe Bailey | download | |
HIA Phase 1 | HIA - Kudusberg | Katie Smuts | download | |
Heritage Scoping | Letter: PROPOSED AMENDMENTS TO THE EMPR OF THE OYA WEF AS PREVIOUSLY APPROVED BY HWC AND SAHRA (CASE NO. 15789) | Jenna Lavin | download, download | |
Heritage Impact Assessment Specialist Reports | Oya WEF Amendment Letter | Katie Smuts | download | |
Palaeontological Specialist Reports | Oya WEF Amendment Letter - Palaeontology | Elize Butler | download | |
Heritage Impact Assessment Specialist Reports | Oya WEF Confirmation Letters | Katie Smuts, Elize Butler | download, download, download, download | |
HIA Phase 3 | Oya WEF HMP | Jenna Lavin | download | |
HIA Phase 3 | Oya WEF Walkdown Report | Jenna Lavin, Nicholas Wiltshire, Dewald Wilken, Nikki Mann | ||
PIA Phase 1 | PIA - Kudusberg | John Almond | download | |
Visual Impact Assessment | VIA - Kudusberg | Sivest PPP | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document | |
Final Comment | Access Document | |
Final Comment | Access Document |