CaseDetails
    Summary
    Case ID
    15567
    Case Status
    Heritage Authority(s)
    SAHRA
    NBKB
    Proposal Description
    Eskom is proposing to build a 14km 22kV powerline and dismantle the Herbet Vaalfarm existing line.
    The proposed line will run parallel to the existing line within the same servitude (10 m apart). The proposed 14 km line will transverse between four farms and supply power to customers in the Douglas area, Northern Cape.
    Author
    Luba.ndzimande
    Last modified
    21/10/2023 - 13:14
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Decision Access Document