Proposal Description
Eskom is proposing to build a 14km 22kV powerline and dismantle the Herbet Vaalfarm existing line.
The proposed line will run parallel to the existing line within the same servitude (10 m apart). The proposed 14 km line will transverse between four farms and supply power to customers in the Douglas area, Northern Cape.
The proposed line will run parallel to the existing line within the same servitude (10 m apart). The proposed 14 km line will transverse between four farms and supply power to customers in the Douglas area, Northern Cape.
Post date
25/06/2021 - 09:56
Last modified
21/10/2023 - 13:14
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document |