CaseDetails
Summary
Case ID
15902
Case Status
Official Reference
17039
Proposal Description
Eskom Holdings, Mpumalanga Operating Unit is proposing to build a 1.557 km 11kV powerline from the SMY Moya feeder. The project will be within the Nyamazaan 647 JU property, Ehlanzeni District municipality, Mbombela Local Municipality, Mpumalanga province.
The project will involve the digging of 2X2m and 2,4m deep holes to plant 14m wooden poles and install transformer to interconnect with another feeder.
The project will involve the digging of 2X2m and 2,4m deep holes to plant 14m wooden poles and install transformer to interconnect with another feeder.
Post date
30/08/2021 - 12:53
Last modified
23/10/2023 - 17:56
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document |