    Proposal Description
    The scope includes pipe repair of approximate 75m long pipe from manhole to manhole and installation of approximately 85m of erosion protection using combination gabions and rip rap by conventional open trench method for normal ground works and by open trench mainly. The scope of work will also incorporate at least the following activities:
    Pipe repair
    • Installation of a new 250mm uPVC sewer pipe approximately 75m long from manhole to manhole
    Erosion protection of the following:
    • Rip rap
    • Gabion boxes
    • Gabion reno mattresses
    • Import backfill material
    • Earthworks excavation and compaction
    The existing clay sewer pipe has washed away by the river/ flooding due to riverbank being also scoured. The temporary connection of new PVC pipe have been installed/ reconnected to existing pipe to avoid effluent being discharged on the stream