CaseDetails
    Summary
    Case ID
    16369
    Case Status
    Heritage Authority(s)
    SAHRA
    NBKB
    Proposal Description
    Great Karoo Renewable Energy (Pty) Ltd is proposing the development of a commercial wind farm and associated infrastructure on a site located approximately 35km south-west of Richmond and 80km south-east of Victoria West, within the Ubuntu Local Municipality and the Pixley Ka Seme District Municipality in the Northern Cape Province.
    A preferred project site with an extent of ~29 909ha and a development area of ~4 544ha within the project site has been identified by Great Karoo Renewable Energy (Pty) Ltd as a technically suitable area for the development of the Angora Wind Farm with a contracted capacity of up to 140MW that can accommodate up to 45 turbines. The development area consists of the four (4) affected properties, which include:
    Portion 11 of Farm Gegundefontein 53
    Portion 0 of Farm Vogelstruisfontein 84
    Portion 1 of Farm Rondavel 85
    Portion 0 of Farm Rondavel 85
    The Angora Wind Farm project site is proposed to accommodate the following infrastructure, which will enable the wind farm to supply a contracted capacity of up to 140MW:
    Up to 45 wind turbines with a maximum hub height of up to 170m. The tip height of the turbines will be up to 250m.
    Concrete turbine foundations to support the turbine hardstands.
    Inverters and transformers.
    Temporary laydown areas which will accommodate storage and assembly areas.
    Cabling between the turbines, to be laid underground where practical.
    A temporary concrete batching plant.
    33/132kV onsite facility substation.
    Underground cabling from the onsite substation to the 132kV collector substation.
    Electrical and auxiliary equipment required at the collector substation that serves that wind energy facility, including switchyard/bay, control building, fences, etc.
    Battery Energy Storage System (BESS).
    Access roads and internal distribution roads.
    Site offices and maintenance buildings, including workshop areas for maintenance and storage.
    The wind farm is proposed in response to the identified objectives of the national and provincial government and local and district municipalities to develop renewable energy facilities for power generation purposes. It is the developer’s intention to bid the Angora Wind Farm under the Department of Mineral Resources and Energy’s (DMRE’s) Renewable Energy Independent Power Producer Procurement (REIPPP) Programme, with the aim of evacuating the generated power into the national grid. This will aid in the diversification and stabilisation of the country’s electricity supply, in line with the objectives of the Integrated Resource Plan (IRP) with the Angora Wind Farm set to inject up to 140MW into the national grid.
    Author
    jenna.lavin
    Last modified
    30/09/2024 - 07:52
    Reports
    Heritage Reports linked to this Case
    Heritage Scoping Heritage Screener - Angora REF (Great Karoo) Jenna Lavin download
    HIA Phase 1 HIA: Angora WEF Jenna Lavin download
    Official
    Case Officers
    Action Tags
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document
      Interim Comment Access Document