Proposal Description
De Beers Venetia Mine (hereto referred to as De Beers) proposes the development of a Photovoltaic(PV) solar energy facility (SEF) to reduce its consumption of grid-supplied power by using solar power. The solar energy facility will be run by a third-party power producer, which will be contracted through a Special Purpose Vehicle (SPV), set up by De Beers.
The Venetia Diamond Mine is situated approximately 80 km west of Musina and 36km north east ofAlldays in the Limpopo Province.
The Venetia Diamond Mine is situated approximately 80 km west of Musina and 36km north east ofAlldays in the Limpopo Province.
Post date
23/11/2021 - 16:16
Last modified
23/10/2023 - 17:57
Reports
HIA Phase 1 | A phase 1 HIA Report for the proposed Venetia Mine Solar PV Facility | Eric Ndivhuho Mathoho | download |