CaseDetails
Summary
Case ID
16552
Case Status
Official Reference
SAH21/17740
Proposal Description
Siza Water proposes the construction of the new trunk sewer main from Caledon Estate pump station to Compensation pump station. The project will comprise a new DN200 HDPE pumped main approximately 350m long from the existing Caledon Estate pump station to a new stilling chamber and a new DN160 PVC gravity main approximately 1850m long from the new stilling chamber to the existing Compensation pump station. The existing Caledon Estate pump station (pumps, pipework, electrical power supply, and control instruments) will also be upgraded.
Post date
28/12/2021 - 11:53
Last modified
22/08/2024 - 14:09
Reports
HIA Phase 1 | Caledon sewer pipeline project | Jean Beater | download, download |
Official Use
Official
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |