    Proposal Description
    Background
    Vetlaagte Farm consists of 3x PV farms of which Environmental Authorisation was obtained in 2012/14
    The 3x PV farms will each have a Switching Station as well as a grid connection connecting the PV farm to the new MTS
    The new MTS will connect via Loop In Loop Out (LILO) power lines to an existing 400kV power line

    Project components and areas for assessment
    3x grid connections WITH A 200M CORRIDOR
    3x switching stations (note that the Switching Stations fall within the 200m corridor)
    Main Transmission Substation – note that there are two site alternatives within the assessment area. These alternative sites need to be assessed and other sites recommended should these sites not be suitable.
    LILO lines to connect the MTS to the existing 400kV lines
    The entire assessment area (as per info provided for quoting purposes) needs to be investigated and no go areas demarcated.

    General
    The grid connections connecting PV1 and PV2 are running adjacent to each other and to the direct east of an existing 132kV line (the existing line is in red in the map below)
    The PV3 grid connection and switching station are situated within the assessment area.
    Author
    jenna.lavin
    Last modified
    23/10/2023 - 17:57
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports Addemdum: Vetlaagte Heritage Jenna Lavin download
    AIA Phase 2 Detailed Site Recording at 34471 Nicholas Wiltshire download
    Heritage Scoping Heritage Screener: Vetlaagte Infrastructure Jenna Lavin download
    HIA Letter of Exemption Heritage Screener: Vetlaagte Supplementary Report Jenna Lavin download
    HIA Phase 1 HIA: Vetlaagte Grid Infrastructure Jenna Lavin, Nicholas Wiltshire download, download, download, download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Letter Access Document
      Final Comment Access Document