CaseDetails
Summary
Case ID
16848
Case Status
Proposal Description
The Safari Rural substation is an 88/11kV substation supplying the South African Nuclear Energy Corporation SOC Limited (NECSA). The substation is currently supplied through 2 x 88kV underground oil filled cables from the Lomond Main Transmission Substation (MTS). The cables sometimes lose pressure resulting in a loss of supply to the Safari Rural substation.
To address the above situation, Eskom identified the following proposed project:
• Construction of a 1 x 88kV chickadee powerline of ±2.3km from Lomond MTS to Safari Rural substation. Steel structures will be utilised to build the HV powerline.
• Part of the 2 x 88kV underground oil filled cables will be dismantled and sealed off.
• The Safari Rural substation will be refurbished by replacing old and redundant equipment.
To address the above situation, Eskom identified the following proposed project:
• Construction of a 1 x 88kV chickadee powerline of ±2.3km from Lomond MTS to Safari Rural substation. Steel structures will be utilised to build the HV powerline.
• Part of the 2 x 88kV underground oil filled cables will be dismantled and sealed off.
• The Safari Rural substation will be refurbished by replacing old and redundant equipment.
Post date
04/03/2022 - 14:33
Last modified
23/10/2023 - 17:57
Reports
HIA Phase 1 | PHASE 1 ARCHAEOLOGICAL/HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED LOMOND-SAFARI 88 KV POWERLINE CONSTRUCTION | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document | |
Final Comment | Access Document |