    Proposal Description
    Wagt Solar PV1 (Pty) Ltd is proposing the development of a Photovoltaic (PV) Solar Energy Facility and associated infrastructure on Farm Wag 'n Bietjie Annex C 137 and Farm Wag 'n Bietjie No. 5 located approximately 10km east of De Aar within the Emthanjeni Local Municipality in the Northern Cape Province. The facility will have a contracted capacity of up to 100MW and will be known as Wagt Solar PV1. The project is planned as part of a cluster of renewable energy facilities known as Pixley Park, which includes three (3) additional 100MW Solar PV Facilities (Rietfontein Solar PV1, Carolus PV1, and Fontain Solar PV1), and grid connection infrastructure connecting the
    facilities to the existing Hydra Substation. The projects will all connect to the new Vetlaagte Main Transmission Substation (MTS) via the Wag ‘n Bietjie MTS.
    Infrastructure associated with the Solar PV Facility will include the following:
    Solar PV array comprising bifacial PV modules and mounting structures, using single axis tracking technology
    Inverters and transformers
    Cabling between the panels
    Battery Energy Storage System (BESS)
    Laydown areas, construction camps, site offices
    12m wide Access Road and entrance gate to the project site and switching station
    6m wide internal distribution roads
    Operations and Maintenance Building, Site Offices, Ablutions with conservancy tanks, Storage Warehouse, workshop, Guard House
    Onsite 132kV IPP Substation, including the HV Step-up transformer, and MV Interconnection building
    132kV Overhead Power Line (OHPL) – 30m height from the switching station to the Main Transmission Substation (MTS) located on farms Vetlaagte and Wagt, which is to be handed back to Eskom (a separate EA is being applied for in this regard)
    Extension of the 132kV Busbar at the MTS
    132kV Feeder Bay at the MTS Extension of the 400kV Busbar at the MTS
    Installation of a new 400/132kV Transformer and bay at the MTS

    A development footprint of approximately 737ha has been identified within the broader project site (approximately 8 200ha in extent), by the developer for the development of the Wagt Solar PV1 Facility, which is proposed in response to the identified objectives of the national and provincial government and local and district municipalities to develop renewable energy facilities for power generation purposes. It is the developer’s intention to bid the proposed project under the Department of Mineral Resources and Energy’s (DMRE’s) Renewable Energy Independent Power Producer Procurement (REIPPP) Programme (or similar programme), with the aim of evacuating the generated power into the national grid. This will aid in the diversification and stabilisation of the country’s electricity supply, in line with the objectives of the Integrated Resource Plan (IRP), with Wagt Solar PV1 set to inject up to 100MW into the national grid.
    Author
    jenna.lavin
    Last modified
    23/10/2023 - 17:58
    Reports
    Heritage Reports linked to this Case
    Heritage Scoping Heritage Screener: Wagt Solar PV Jenna Lavin download
    HIA Phase 1 HIA: Wagt PV Jenna Lavin download
    Official
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document
      Interim Comment Access Document
      Interim Comment Access Document
      Interim Comment Access Document