CaseDetails
    Summary
    Case ID
    17143
    Case Status
    Heritage Authority(s)
    SAHRA
    LIHRA
    Official Reference

    18393

    Proposal Description
    This project is initiated by Eskom to ensure continuous reliable supply for the Steelpoort Area. The proposed construction of a ± 12km 132kV Bersfort line between Maphuta MTS (Uchoba Substation) and Der Brochen Substation is required to strengthen the network. It is crucial to improve the reliability and quality of supply of the network.
    The proposed project is located to the south of Steelpoort and Ga-Mampuru, east of Ga-Malekana and the De Hoop dam, in the jurisdiction of Fetakgomo Tubatse Local Municipality, Sekhukhune District Municipality, Limpopo Province. The project is proposed on Portions 0, 6, 7, 1, of the Farm Dwars Rivier 372 KT and Portions 3, 7, 0 of the Farm Thorncliffe 374 KT.
    Author
    ria.pretorius
    Last modified
    21/10/2023 - 13:24
    Reports
    Heritage Reports linked to this Case
    HIA Phase 1 HIA Uchoba Der Brochen Jaco van der Walt download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document