Proposal Description
EnpowerMachite has proposed the development of a new power line, namely the Bethal_Emzinoni 88kV powerline and a 40 MVA Substation. The project constitutes of a high voltage power line starting from Eskom substation, which is in the Northern Part of Bethal Town, ending at Emzinoni township, where the new 40MVA substation will be located.
Post date
11/05/2022 - 10:53
Last modified
23/10/2023 - 17:58
Reports
HIA Phase 1 | HIA for the proposed Bethal – Emzinoni 88kV | Edward Matenga |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |