CaseDetails
Summary
Case ID
17709
Case Status
Official Reference
19017
Proposal Description
Motivation for Exemption from a full Phase I Heritage Impact Assessment - Environmental Impact Assessment for the Proposed construction of a 3.2 km long, 132kV overhead line (to be operated at 88kV) and a 88 kV substation (To be known as Brakpan Tailings dam Substation) located on Portion 77 of the farm Withok 131IR, Portion 76 of the farm Withok 131IR and Portion 5
of the farm Rooikraal 156IR, City of Ekurhuleni Metropolitan Municipality, Gauteng Province. APAC022/61
of the farm Rooikraal 156IR, City of Ekurhuleni Metropolitan Municipality, Gauteng Province. APAC022/61
Post date
09/07/2022 - 10:12
Last modified
21/10/2023 - 13:26
Reports
HIA Letter of Exemption | Brakpan Tailings Dam OVH Line & New Substation | Anton Pelser | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |