CaseDetails
    Summary
    Case ID
    17910
    Case Status
    Heritage Authority(s)
    SAHRA
    Proposal Description
    Eskom Holdings SOC Ltd, Limlanga Cluster intends to construct the 22kv powerline for the above-mentioned project. The powerline will include the length above 300m which will be connected to the existing powerline in the area (refer to the Span plan sheets and the Pegging Coordinates for more information). The line will be constructed in Bolubedu, Madumeleng Village in Letaba Local Municipality under Mopani District in Limpopo Province. Environmental Screening of the powerline route was conducted during mapping of the village and pegging of the route the by Survey team and site verification by Environmental Practitioner. No Heritage resources outlined on item 6.3 of the DESD were observed on site.
    Author
    tshifhiwa.matamela
    Last modified
    21/10/2023 - 13:26
      Location
      Location