    Proposal Description
    The activities entail the development of an up to 400 MW photovoltaic solar energy facility and associated
    infrastructure (including an on-site substation, grid connection, access roads and battery storage system). The facility will be located on Farm Die Vlakte No. 1950 and the Remaining extent of Farm Brandkop No. 702, Registration
    Division Bloemfontein RD, situated within the Mangaung Metropolitan Municipality area of jurisdiction. The city of
    Bloemfontein is located approximately 7km north of the proposed development (refer to the attached locality map).

    The project entails the generation of up to 400MW electrical power through photovoltaic (PV) panels. The
    total extent of the project will be approximately 800hectares (including supporting infrastructure on site). The
    property on which the facility is to be constructed will be leased by Mira Solar PV Project One (Pty) Ltd from the
    property owner, for the lifespan of the project (minimum of 20 years).
    Author
    roschel.maharaj
    Last modified
    09/07/2024 - 11:15
    Reports
    Heritage Reports linked to this Case
    Mira Scoping HIA download, download
    Mira Scoping PIA download, download
    PIA Phase 1 Mira Solar PV Project One: PIA Elize Butler download
    HIA Phase 1 Phase 1 Cultural Heritage Impact Assessment: HIA Johnny van Schalkwyk download
    Official
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document
      Interim Comment Access Document
      Interim Comment Access Document
      Interim Comment Access Document