South Africa Mainstream Renewable Power Developments (Pty) Ltd ("Mainstream") is proposing to develop a 132kV overhead power line and 132kV portion of the Eskom Switching Station and associated grid connection infrastructure to support the proposed 100MW Sungazer Solar PV Facility near the town of Bultfontein in the Free State Province. The proposed grid connection infrastructure is required to evacuate and feed electricity generated by the PV facility to the national grid.
Post date
17/08/2023 - 09:27
Last modified
03/06/2024 - 15:35
Reports
Heritage Impact Assessment Specialist Reports | Sungazer EGI Heritage Impact Assessment | Jayson Orton | download | |
PIA Phase 1 | Sungazer EGI Palaeontological Impact Assessment | Elize Butler | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |