We acknowledge receipt of your application for a permit to carry out work on the above property. The KZN Amafa and Research Institute (the Institute) reviewed the application on the 27 July 2022 and additional documentation reviewed on the 31 August 2022.
Please be advised as follows:-
(1) The Institute was unable to consider the merits of the application as the work had already commenced, alternatively, has been completed;
(2) As a result, a permit cannot now be issued;
(3) We would like to draw your attention to the fact that your failure to obtain a permit prior to the commencement of the work, is in contravention of the provisions of the KwaZulu-Natal Amafa and Research Institute Act (5 of 2018), and as such is a criminal offence for which you may be prosecuted;
(4) However, the Institute has decided to condone your failure to obtain a permit, as required, on condition that the work was conducted strictly in accordance with drawing number Z2/4021, dated August 2021, drawn by Z.P (Zane Osborne Architectural & Design) , received by the Institute , and that all the work shown on the application is completed within a calendar year of the date of this letter.
(5) Prior written approval from the Institute is required for any deviation to the approved plans.
(6) No legal action will be instituted against you in this instance.
CaseReference
Applicable legislation
34(1)
Decision Date
Committee
Decision Status
Case Decision
98 Wylie Rd.pdf (120.28 KB)