Applicable legislation
38(4)
Decision Date
Decision Status
Case Decision

Final Decision
The SAHRA Archaeology, Palaeontology and Meteorites (APM) Unit has no objections to the proposed development and supports the recommendations of the heritage specialists. The recommendations of the specialists and the following conditions must be included in the Final EMPr:

A Chance Finds Procedure must be developed and implemented as part of the EMPr. These procedures must be submitted to SAHRA for review and comment prior to construction; and
If any evidence of archaeological sites or remains (e.g. remnants of stone-made structures, indigenous ceramics, bones, stone artefacts, ostrich eggshell fragments, charcoal and ash concentrations), fossils or other categories of heritage resources are found during the proposed development, SAHRA APM Unit (Natasha Higgitt/Phillip Hine 021 462 5402) must be alerted. If unmarked human burials are uncovered, the SAHRA Burial Grounds and Graves (BGG) Unit (Thingahangwi Tshivhase/Mimi Seetelo 012 320 8490), must be alerted immediately. A professional archaeologist or palaeontologist, depending on the nature of the finds, must be contracted as soon as possible to inspect the findings. If the newly discovered heritage resources prove to be of archaeological or palaeontological significance, a Phase 2 rescue operation may be required subject to permits issued by SAHRA.