Interim Comment
The SAHRA Archaeology, Palaeontology and Meteorites (APM) Unit requests that the PIA be revised to assess powerline options 4, A and B. The revised PIA must include a fieldwork survey of the outstanding powerline options. Further comments will be issued upon receipt of the above requested report.
The applicant is advised to extend the EA process in terms of section 19(1)b of the NEMA EIA Regulations in order to comply with this comment.