CaseReference
Applicable legislation
38(3)
38(8)
Decision Date
Committee
Decision Status
Case Decision
Interim Comment
The SAHRA Archaeology, Palaeontology and Meteorites (APM) Unit requests that the pending assessment of the impact to palaeontological resources comply with the 2012 Minimum Standards: Palaeontological Component of Heritage Impact Assessments.
Additionally, SAHRA requests that a more comprehensive survey be conducted during the EIA phase as it was noted that the initial survey as part of the HIA was minimal. The HIA must be revised to include the results of the requested survey. Further comments will be issued upon receipt of the above pending reports and the draft EIA inclusive of appendices.