Case Decision
Interim Comment
SAHRA is satisfied that there are no impacts to the identified grave site LWUA 1 and SP12. The 30 m buffer from identified graves must be adhered to with the exception of SP12, where the 22 m between the grave and the construction must be maintained with continued monitoring of all construction in the area by the ECO.
Regarding the identified human remains within the trench, SAHRA requests a full report of the find be submitted by an archaeologist i.e. location of the find with a map, surface indictors, possible construction alternatives, including the proposed mitigation measures.
Further comments will be provided upon receipt of the above requested report.