This application involves the following components, including but not limited to, within the footprint applied for:
• Guard house/ Access Control for security purposes and for access control. The guardhouse is developed to accommodate guards who will be protecting the water service infrastructure and for controlling the access to both the reservoirs and the WTW;
• Main administration building which includes a control room, the laboratory and the main administration areas (i.e., ablutions, workshop and store room);
• Sludge lagoons to dry the sludge produced from the WTW;
• Machine Room;
• A Chemical Storage Area for the safe handling and storage of chemicals delivered to and stored on site; and
• Access and Internal Roads.
• Guard house/ Access Control for security purposes and for access control. The guardhouse is developed to accommodate guards who will be protecting the water service infrastructure and for controlling the access to both the reservoirs and the WTW;
• Main administration building which includes a control room, the laboratory and the main administration areas (i.e., ablutions, workshop and store room);
• Sludge lagoons to dry the sludge produced from the WTW;
• Machine Room;
• A Chemical Storage Area for the safe handling and storage of chemicals delivered to and stored on site; and
• Access and Internal Roads.
Post date
18/10/2023 - 17:00
Last modified
18/07/2024 - 11:05
Reports
Heritage Impact Assessment Specialist Reports | Heritage Impact Assessment | Natanya Whitehorn | download |
Official Use
Official
Case Officers
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |