    Proposal Description
    ABO Wind renewable energies (Pty) Ltd (The Applicant) is proposing to construct the ABO Ujekamanzi
    Main Transmission Substation (MTS) and Loop-In-Loop-Out (LILO) Powerline 1 and associated
    infrastructure approximately 20 km north-east of Amersfoort in the Dr Pixley Ka Isaka Seme Local
    Municipality, in Mpumalanga (Figure 1) (DARDLEA Reference Number: 1/3/1/16/1G-292). The overall
    objective of the proposed development is to feed electricity generated by the ABO Ujekamanzi Wind
    Energy Facilities (WEFs) (separate EIA applications) into the national grid. The MTS and LILO will be
    located within the WEF site boundary.
    SiVEST Environmental Division has subsequently been appointed as the independent Environmental
    Assessment Practitioner (EAP) to undertake the Environmental Impact Assessment (EIA) process for
    the proposed construction and operation of the ABO Ujekamanzi MTS and LILO 1. The proposed
    development requires an Environmental Authorisation (EA) from the Provincial Department of
    Agriculture, Rural Development and Environmental Affairs (DARDLEA). The EIA for the proposed
    development will be conducted in terms of the EIA Regulations, 2014 (as amended) promulgated in
    terms of Chapter 5 of the NEMA. In terms of these regulations, a full EIA process is required for the
    proposed development. All relevant legislation and guidelines will be consulted during the EIA process
    and will be complied with at all times.
    One additional MTS and LILO is concurrently being considered on the adjacent properties and are
    assessed by way of a separate impact assessment process in terms of the 2014 Environmental Impact
    Assessment Regulations (GN No. R982, as amended) for listed activities contained within Listing
    Notices 1, 2 and 3 (GN R983, R984 and R985, as amended). This project is known as the ABO
    Ujekamanzi MTS AND LILO 2 (DARDLEA Reference Number: 1/3/1/16/1G-293).
    The WEF developments are also being proposed by the developer, namely ABO Ujekamanzi Wind
    Energy Facility 1 (Pty) Ltd and ABO Ujekamanzi Wind Energy Facility 2 (Pty) Ltd and includes the
    proposed construction of a Wind Energy Facility with a total generation capacity of 650MWac per WEF,
    which will be assessed in separate EIA’s to be submitted to the Department of Forestry, Fisheries and
    Environment (DFFE) (DFFE Reference Numbers: 14-12-16-3-3-2-2356/14-12-16-3-3-2-2357).
    The overall objective of the proposed ABO Ujekamanzi WEF projects (which includes the 2 WEFs, Main
    Transmission Substation, LILO Power Line and associated infrastructure) is to generate electricity by
    means of renewable energy technologies, capturing wind energy to feed into the national grid, which
    will be procured under either the Renewable Energy Independent Power Producer Procurement
    Province(s): Mpumalanga
    Author
    andrea.gibb
    Last modified
    17/11/2023 - 08:25
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports Heritage Impact Assessment Jenna Lavin download
    Official
    Case Officers
      Location
      Location