Applicable legislation
37
Decision Date
Committee
Decision Status
Case Decision

PROPOSED ADDITION AND ALTERATION ON PORTION 4 OF ERF 230 BEING AT 33 EARL HAIG ROAD, MORNINGSIDE, DURBAN.

Please be advised as follows: -

Download and complete Form I with plans indicating the illegal work, and pay R10 000;

Separate work already done illegally with work still outstanding. Download and complete Form A for this purpose.

Each Form must be accompanied by its own set of plans, showing work already done for I and those outstanding for Form A.

Written responses/requests for review of the decision taken must be received via email to [email protected] within 30 days of the date of this letter or any decision contained herein will be considered final. 

THIS LETTER DOES NOT CONSTITUTE FORMAL APPROVAL OF THE PROPOSAL SUBMITTED TO THE INSTITUTE, UNAUTHORISED WORK CARRIED OUT ON THE ABOVE SITE WILL BE IN CONTRAVENTION OF THE KWA-ZULU NATAL AMAFA AND RESEARCH INSTITUTE ACT (5 of 2018)