The expansion proposal includes the following –
Increase production by 150 tons phase 1 / 1.75 ha (wet weight per annum)
Increase production by 150 tons phase 2 / 1.75 ha (wet weight per annum)
Footprint of the new production area = 1.75 ha + 1.75 ha = 3.5 ha / 300 tons
Construction of lined reservoir for containment of sea water for use during load-shedding – 410 000 m3 / 2 ha (no dam wall)
Solar – 4 ha area / 4 MW
Additional pipelines to new production area to join into existing network – 4 lines @ 600 m x 500 mm, delivering 1600 m3 / hour – located alongside existing pipeline within disturbed area
Increase pumphouse by 40m²
The total expansion will comprise 9.5ha with an increased production output by 300 tons wet weight per annum.
Province(s): Western Cape
Increase production by 150 tons phase 1 / 1.75 ha (wet weight per annum)
Increase production by 150 tons phase 2 / 1.75 ha (wet weight per annum)
Footprint of the new production area = 1.75 ha + 1.75 ha = 3.5 ha / 300 tons
Construction of lined reservoir for containment of sea water for use during load-shedding – 410 000 m3 / 2 ha (no dam wall)
Solar – 4 ha area / 4 MW
Additional pipelines to new production area to join into existing network – 4 lines @ 600 m x 500 mm, delivering 1600 m3 / hour – located alongside existing pipeline within disturbed area
Increase pumphouse by 40m²
The total expansion will comprise 9.5ha with an increased production output by 300 tons wet weight per annum.
Province(s): Western Cape
Post date
04/03/2024 - 14:57
Last modified
21/05/2025 - 15:58
Reports
HIA Phase 1 | Proposed Romansbaai Abalone Farm, Gansbaai | Jonathan Kaplan | download, download, download, download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document | |