    Proposal Description
    The proposed project entails the development of the Anker grid connection infrastructure which consists of 132kV single/double-circuit overhead power line with the associated infrastructure. A 400m wide (including temporary working area), grid connection corridor is being assessed for the placement of the powerline route. The length of the powerline is dependent on which alternative is authorised.
    The alternatives are detailed below:
    Alternative (Preferred) route 1: ~0.57km in length.
    Alternative route 2: ~3.1km in length.
    Alternative route 3: ~4.67km in length
    The Anker power line is proposed to connect into the existing Eskom Everest or Leander Substations, or a switching station in proximity to the powerline. A service road beneath the powerline is required for maintenance purposes.
    Province(s): Free State
    Author
    carli.steenkamp
    Last modified
    20/11/2024 - 10:36
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports HERITAGE IMPACT ASSESSMENT for the Proposed Grid Connection Infrastructure for the Anker Solar PV Project development Jenna Lavin download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document