    Proposal Description
    The proposed project entails the development of grid connection infrastructure which consists of 132kV single/double-circuit overhead power line with the associated infrastructure on the Remaining Extent of the farm Maatschappy No. 295. A 400m wide (including temporary working area), grid connection corridor is being assessed for the placement of the powerline route. The length of the powerline is dependent on which alternative is authorised. The alternatives are detailed below:
    Preferred route: ~2,1km in length.
    Alternative route 1: ~14,3km in length.
    Alternative route 2: ~7,36km in length
    The preferred alternative will commence at the on-site substation and connect to the proposed Phemelo Solar PV facility on-site substation. The alternative grid connection will commence at the on-site substation and will connect at either the Eskom Everest Substation or the Eskom Leander Substation. A service road beneath the powerline is required for maintenance purposes.
    Province(s): Free State
    Author
    carli.steenkamp
    Last modified
    13/01/2025 - 11:20
    Reports
    Heritage Reports linked to this Case
    HERITAGE & PALAEONTOLOGICAL IMPACT ASSESSMENT Jenna Lavin, Elize Butler download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document
      Interim Comment Access Document