    Proposal Description
    AGES Limpopo is conducting an Environmental Impact Assessment (EIA) process for the proposed Rietfontein-Springs PV Solar Park Project in the Gauteng Province
    The project entails the following:
    -The development of a PV Solar Plant over a surface area of 55ha.
    -The establishment of an OHL grid connection to either the ESKOM Kwathema or Vlakfontein Substations over two possible routes where Route 1 (Kwathema Substation) extends over 420m and Route 2 (Vlakfontein Substation) extends over 2.1km
    Province(s): Gauteng
    Author
    neels.kruger
    Last modified
    04/11/2024 - 09:33
    Reports
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document