CaseDetails
    Summary
    Case ID
    22553
    Heritage Authority(s)
    SAHRA
    NWPHRA
    Proposal Description
    The gravel is on average 2.5 meter thick with a topsoil/overburden layer which varies between 1 to ‎‎1.5 meters. The area that was identified and demarcated is shown on the sketch plan, see ‎sketch plan Figure 2. The gravel reserve on these 5 hectares is estimated at 50’000m³ or ±56’650 ‎tons and the total material to be moved is 50’000m.
    ‎The area will be mined through opencast excavations. Vegetation cover will be stripped, topsoil ‎layer will be removed and stored on the side of the excavation. Overburden will be stripped and ‎placed on the side of the excavation. The diamond bearing gravel is then removed with a 30-ton ‎excavator and placed next to the excavation and loaded onto a tipper truck and taken to the ‎processing area where it will be put through a washing pan for processing. Rough out of the pan and ‎over size stones will be taken back to the excavation for backfilling and the wet puddle will be ‎pumped directly into open excavations. Overburden will be pushed back after wet puddle is dried out ‎and lastly topsoil will be replaced after finale sloping has occurred. Diamond gravel will be sorted ‎and recovered by hand.‎
    At processing area: A Front-end Loader takes the gravel to the 10 feet washing pan which is feds at ‎a rate of 6m³ an hour or 10 ton per hour, 4’800m³ a month. All the rough and oversize stones are ‎first placed back into the bottom of the excavation, hereafter the puddle out of the pan is pumped ‎directly back into the open excavation. After the puddle dried off, the topsoil is put back on top ‎again. The excavations will be 60m in length 10m wide and ±2.5 meters deep on average. It is ‎estimated that two (2) of this excavation will be opened at a time. ‎
    The total estimated reserve of gravel is 50’000m³ taken at a production rate of 4’800m³ a month it ‎will take 24 months to work the estimated reserve of ±50’000m³. The production rate is taken at ‎‎4’800m³/month. The gravel which is relatively shallow (2.5 meter) and the low production rate of the ‎applicant make this 5 hectare to be worked sustainable over a period of two years.‎
    Province(s): North West
    Author
    dera.environmental
    Last modified
    09/05/2024 - 08:48
    Official
    Case Officers
      Location
      Location