    Proposal Description
    Eskom intends to upgrade the Aries-Kronos Powerline to include a 400kV line. Based on the information provided it is understood that the following would be required:
    • Ground truth of the proposed pylon positions and development of a site-specific Environmental Management Programme (EMPr).
    • Undertake a new water use licence application (WULA) for the relevant water use triggers associated with the proposed project.
    • Appy for relevant heritage permits.
    • Apply for relevant protected tree species permits.
    Inventory Reference
    Author
    cheyenne.muthu…
    Last modified
    10/06/2024 - 07:53
    Reports
    Heritage Reports linked to this Case
    Conservation Management Plan Heritage Management Plan: Aries-Kronos 400kV Transmission Power Line Daniel Tasker download
    Official
    Case Officers