Attention: Mncedisi Matinise
Randsilver Investments (Proprietary)
211 Monty Naicker Rd
Durban Central
Durban
4001
UNAUTHORISED ADDITIONS AND ALTERATIONS: Portion 1 of ERF 11760 - 211 Monty Naicker Road
We acknowledge receipt of your application for a permit to carry out work on the above property. The KZN Amafa and Research Institute (the Institute) reviewed the application on the 3 July 2024.
Please be advised as follows:-
(1) The Institute was unable to consider the merits of the application as the work had already commenced, alternatively, has been completed;
(2) As a result, a permit cannot now be issued;
(3) We would like to draw your attention to the fact that your failure to obtain a permit prior¬ to the commencement of the work, is in contravention of the provisions of the KwaZulu-Natal Amafa and Research Institute Act (5 of 2018), and as such is a criminal offence for which you may be prosecuted;
(4) However, the Institute has decided to condone your failure to obtain a permit, as required, on condition that the work was conducted strictly in accordance with drawing numbers 001 - 007, dated 04/13/2022 and drawn by N.G (KZN Architects), the property graded IIIC received by The Institute on the 25/06/2024 and that all the work shown on the application is completed within a calendar year of the date of this letter.
(5) Prior written approval from the Institute is required for any deviation to the approved plans.
(6) No legal action will be instituted against you in this instance.