CaseDetails
Summary
Case ID
23010
Case Status
Proposal Description
Heritage Impact Assessment for the Proposed Poseidon North 400 to 132 Kv MTS near Craddock in the Inxuba Yethemba Municipality, Eastern Cape Province. Eskom intends to construct a new 132 Kv line from an existing 400Kv line to a proposed substation. There are two proposed positions with a preferred site and position and an alternative. The preferred location lies north of the Great Fish River, 5km NW of the N10 bridge on the Great Fish River (Lat: 31°52'35.22"S Long: 25°22'35.18"E). The second site is located south of the Great Fish River, 10km SW of the N10 bridge (Lat: 32° 0'20.19"S Long: 25°24'12.79"E).
Post date
08/07/2024 - 11:19
Last modified
08/07/2024 - 11:19