CaseDetails
Summary
Case ID
23017
Case Status
Proposal Description
The Applicant, Crossroads Green Energy 2 (PTY) Ltd, is proposing the development of the CGE 2 Phase 1 East Grid Connection Infrastructure to connect into the Krypton MTS, which will consist of 132 kV distribution lines, substations & switching stations at each PV facility and the usage of existing access roads, where necessary. The purpose of the grid connection infrastructure will be to connect the authorised Crossroads Green Energy 2 PV Cluster Phase 1 (consisting of 5 Solar PV Projects) to the national grid.
Province(s): Northern Cape
Province(s): Northern Cape
Post date
08/07/2024 - 15:18
Last modified
26/08/2024 - 10:49
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document | |
Interim Comment | Access Document |