Applicable legislation
38(3)
38(8)
Decision Date
Decision Status
Case Decision

Interim Comment

The SAHRA notes the submission of the DBAR and HIA. However, the proposed development is located within an area of very high Palaeontological Sensitivity as per the SAHRIS PalaeoSensitivity map. As such, a field-based Palaeontological Impact Assessment (PIA) and protocol for finds is required. The assessment must be undertaken by a qualified palaeontologist. (See https://www.palaeosa.org/heritage-practitioners.html for a list of qualified palaeontologists). The report must comply with the 2012 Minimum Standards: Palaeontological Components of Heritage Impact Assessments. 

Further comments will be issued upon the submission of the PIA report. The applicant is advised to extend the EA process in terms of section 19(1) of the NEMA EIA regulations in order to address this comment.