Proposal Description
The previously authorized up to 325MW Rondekop Wind Energy Facility (WEF) is located approximately 45 km south-west of Sutherland in the Karoo Hoogland Local Municipality in the Namakwa District Municipality, Northern Cape Province.
It is only partially located within the Komsberg Renewable Energy Development Zone (REDZ) and, as a result, was subjected to a full Environmental Impact Assessment (EIA) process in accordance with the National Environmental Management Act (NEMA) EIA Regulations.
The environmental authorization (EA) for the project was granted on June 13, 2019 (reference number: 14/12/16/3/3/2/1115).
It is important to note that the Rondekop WEF Environmental Management Programme (EMPr) and final layout were not approved as part of the EA issued. Therefore, Rondekop Wind Farm (Pty) Ltd, the applicant, plans to commence the final layout and EMPr approval process concurrently with a Part 2 EA Amendment process.
The amendments being applied for include changes to the turbine specifications, the technical specifications within the authorised area, as well as other administrative changes.
Additionally, the applicant will undertake a separate application for EA for the associated grid infrastructure.
Province(s): Northern Cape
It is only partially located within the Komsberg Renewable Energy Development Zone (REDZ) and, as a result, was subjected to a full Environmental Impact Assessment (EIA) process in accordance with the National Environmental Management Act (NEMA) EIA Regulations.
The environmental authorization (EA) for the project was granted on June 13, 2019 (reference number: 14/12/16/3/3/2/1115).
It is important to note that the Rondekop WEF Environmental Management Programme (EMPr) and final layout were not approved as part of the EA issued. Therefore, Rondekop Wind Farm (Pty) Ltd, the applicant, plans to commence the final layout and EMPr approval process concurrently with a Part 2 EA Amendment process.
The amendments being applied for include changes to the turbine specifications, the technical specifications within the authorised area, as well as other administrative changes.
Additionally, the applicant will undertake a separate application for EA for the associated grid infrastructure.
Province(s): Northern Cape
Post date
12/08/2024 - 10:22
Last modified
05/03/2025 - 14:44
Reports
Heritage Impact Assessment Specialist Reports | Amendment Letter: Rondekop WEF | Jenna Lavin | download | |
Conservation Management Plan | HMP: Rondekop WEF | Jenna Lavin | download | |
Heritage Impact Assessment Specialist Reports | Walkdown Report: Rondekop WEF | Jenna Lavin, Nicholas Wiltshire, Elize Butler | download, download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document | |
Letter | Access Document | |