Applicable legislation
37
Decision Date
Committee
Decision Status
Case Decision

APPROVAL LETTER

Please be advised as follows: -

  1. Section 37(1) of the KZN Amafa and Research Institute Act (5/2018) requires that prior approval be obtained for work on buildings that are, or can reasonably be expected to be, over 60 years of age.
  2. The work that was carried out without approval was carried out at a time when the building was not over 60 years of age. Therefore, no permit was required from the heritage authority at the time the work was carried out.
  3. The building is now over 60 years of age and the formal approval from the heritage authority is required to comply with the provisions of the heritage legislation.
  4. The proposed work did not impact on the heritage value or conservation worthiness of the property which the Institute has graded as (NCW Grade III….).
  5. Provided that the work has been carried out strictly in accordance with Drawing numbers: SUB001-SUB008, REV 02, drawn by Mrs B Naidoo-Radhani and dated 7 February 2024, the Institute has no objection to the regularisation of the work that was carried out on this property before it turned 60 years of age. 
  6. Prior written approval from The Institute is required for any deviation to the approved plans.

Please note that the above property contains a structure(s) protected in terms of the KwaZulu-Natal Amafa and Research Institute Act (5 of 2018), and a permit must be obtained prior to any work being conducted on the property in the future. Failure to do so is a criminal offence punishable by a term of imprisonment or a fine, or both. The property may also be forfeited to the state, or a moratorium may be placed on any development thereon.