The permit application in respect of the above, reviewed on 21 August 2024 reviewed by the KwaZulu-Natal Amafa and Research Institute refers:
Please be advised as follows:
- The committee noted that the application was for a rectification of unauthorized work however it was noted that there was still work that needs to be done on the subject property.
- The committee therefore referred this application for further requirements.
FURTHER REQUIREMENTS
- The applicant was required to submit Form A for the proposed work and drawings for the new work.
- The applicant is required to attach proof of payment for the Form A required.
Written responses/requests for reconsideration of the application or consideration of new information must be loaded to the case on SAHRIS (email [email protected]) within 30 days of the date of this letter or any requirements/decisions contained herein will be considered final. Extensions of this time frame can be requested upon receipt of motivation.
Required additional information or revised drawings must be submitted within six months from the date of this letter or the application will lapse and a new application will be required.
THIS LETTER DOES NOT CONSTITUTE FORMAL APPROVAL OF THE PROPOSAL SUBMITTED TO THE INSTITUTE. UNAUTHORISED WORK CARRIED OUT ON THE ABOVE SITE WILL BE IN CONTRAVENTION OF THE KWAZULU-NATAL AMAFA AND RESEARCH INSTITUTE ACT (NO.5 of 2018).