CaseDetails
Summary
Case ID
23662
Case Status
Official Reference
23662
Proposal Description
Mudzunga Consulting ICT (Pty) Ltd was tasked by the Vombe Environmental Consulting (Pty) Ltd on behalf of the National Transmission Company of South Africa (NTCSA), a subsidiary of Eskom Holdings SOC Limited to carry out a Phase 1 AIA/ HIA for proposed expansion of the Hendrina Substation and associated infrastructure within Steve Tshwete Local Municipality in Nkangala District, Mpumalanga Province.
Province(s): Mpumalanga
Province(s): Mpumalanga
Post date
26/09/2024 - 21:35
Last modified
17/10/2024 - 09:15
Reports
HIA Phase 1 | PROPOSED EXPANSION OF THE HENDRINA SUBSTATION | Trust Mlilo | download | |
PIA Phase 1 | PROPOSED EXPANSION OF THE HENDRINA SUBSTATION | Marion Bamford | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |