Proposal Description
The Applicant is applying, on behalf of Eskom, to construct a 22Kv Powerline from the Balfour substaiton in Mpumalanga to Astral in Gauteng. The proposed powerline is 25km in length and will supply three chicken farms directly with electricity from the Balfour substation.
Province(s): Mpumalanga
Province(s): Mpumalanga
Post date
15/10/2024 - 15:09
Last modified
17/04/2025 - 08:55
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document | |
Interim Comment | Access Document |