Proposal Description
The Proposed Highveld North-West and Lowveld Strengthening Project: Equipping of Existing Borutho and Silimela Substations and Development of Borutho-Silimela 150km 400kv Transmission Line and Associated Infrastructure, within the Capricorn, Sekhukhune and Waterberg District Municipalities, Limpopo Province
Province(s): Limpopo
Province(s): Limpopo
Post date
21/10/2024 - 01:04
Last modified
28/10/2024 - 07:46
Reports
PIA Desktop | Palaeontological Impact Assessment for the proposed Boruthro – Silimela 400 kV OHPL strengthening project | Marion Bamford | download | |
HIA Phase 1 | Phase I Heritage Impact Assessment for the Proposed Development Of Borutho - Silimela Powerline | Makhosazana Mngomezulu | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document |