The Granite is situated on this demarcated area on average 4.5 meters deep. The identified and demarcated which are 2.5 hectares in total, includes the entire mining area. The whole of the 2.5 hectares will be used for mining. The Granite reserve on these 2.5 hectares is estimated at 9’000 m³. (It is taken that 10% of the material in situ is sellable, thus 90% waste).
Topsoil and vegetation will be stripped and stockpiled separately for final rehabilitation. The application area will be mined through blasting and opencast excavations where the Granite will be drilled, blast and cut with a diamond saw into blocks. The blocks are then removed with a frond-end loader to the stockpile/dressing area for dressing and loading onto the trucks.
The Granite blocks will be transported to the clients at a rate of 375m³ a month. The total estimated reserve of Granite/Syenite (MA) is 9’000m³ taken at a production rate of 375m³ a month it will take 30 months to work the estimated reserve of 9’000 m³. The Granite which is 4.5m thick and the relatively low production rate of this operation make these 2,5 hectares to be worked sustainable over the initial period of two years and renewal periods of 3 years. The area will be mined through opencast excavations.
Province(s): North West
Topsoil and vegetation will be stripped and stockpiled separately for final rehabilitation. The application area will be mined through blasting and opencast excavations where the Granite will be drilled, blast and cut with a diamond saw into blocks. The blocks are then removed with a frond-end loader to the stockpile/dressing area for dressing and loading onto the trucks.
The Granite blocks will be transported to the clients at a rate of 375m³ a month. The total estimated reserve of Granite/Syenite (MA) is 9’000m³ taken at a production rate of 375m³ a month it will take 30 months to work the estimated reserve of 9’000 m³. The Granite which is 4.5m thick and the relatively low production rate of this operation make these 2,5 hectares to be worked sustainable over the initial period of two years and renewal periods of 3 years. The area will be mined through opencast excavations.
Province(s): North West
Post date
26/11/2024 - 11:28
Last modified
28/01/2025 - 07:58
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|