    Proposal Description
    SACE Projects (Pty) Ltd. plans to develop, construct and operate a Solar PV facility, located approximately 4 km
    north of Benoni in the Gauteng Province. The project site is situated in situated within Ward 25 of the of
    Ekurhuleni Metropolitan Municipality. The development will be on the Remaining Extent of the Farm Putfontein
    26 IR, East Rand region of Gauteng. The anticipated lifespan of the Solar PV Facility is 25 years and construction
    is anticipated to be between 8 and 14 months.

    The proposed Ravenna Solar PV facility will have a total output of up to 10-20 MW. The Solar PV facility will also
    include a powerline in order to connect the Solar PV facility to the existing Eskom Substation (this will be applied
    for in a separate environmental application). The Solar PV facility will also include temporary and permanent
    laydown areas, and access roads and a construction compound (CC) area. The extent of the proposed
    development area is approximately 17.3ha