CaseDetails
    Summary
    Case ID
    24574
    Case Status
    Heritage Authority(s)
    SAHRA
    NBKB
    Proposal Description
    Emoyeni Project Management (Pty) Ltd proposes the development of two permanent soil berms to support the construction of the second phase of the 132kV/400kV Gamma Substation yard (DFFE Ref.: 12/12/20/873). The berms are required to store excess spoil material generated during excavation activities within the authorised Gamma Substation yard. The proposed development involves two berm area strategically located on either side of the existing Gamma Substation:

    • Northern Berm: Envisioned to cover approximately 11.7 hectares
    • Southern Berm: Envisioned to cover approximately 7,69 hectares

    The proposed soil berms will play a critical role in enabling the construction of the second phase of the Gamma Substation, which includes the development of the 132kV/400kV substation yard and turn in of the existing 400kV Droerivier-Hydra 2 Overhead Powerline (OHL) and associated infrastructure. This second phase is essential to facilitate the connection of the authorised Umsinde Emoyeni Wind Energy Facility (WEF) (DFFE Ref.: 14/12/16/3/3/2/686), Khangela Emoyeni Wind Energy Facility (DFFE Ref.: 14/12/16/3/3/2/687), and Ishwati Emoyeni Wind Energy Facility (DFFE Ref.: 12/12/20/2351) which are currently under construction. The Umsinde Emoyeni WEF has been registered as a Strategic Infrastructure Project (SIP).

    On-site operations for the soil berms development are expected to last approximately 12-18 months and the proposed project will include:
    » Two permanent soil berms:
     The Northern Berm is envisioned to cover approximately 11,7 Ha.
     The Southern Berm is envisioned to cover approximately 7.69 Ha
    » Proposed internal gravel access roads which will be up to 8m wide.
    » Existing access road will be used as far as possible and widened up to 8m
    » Fill gradient of approximately 1:4 and anticipated volume of 119 330m3
    » Maximum fill height of approximately 2.1m.

    The proposed construction of the soil berms will be located within Portion 1 of the Farm Uit Vlugt Fontein 265 adjacent to the authorised Gamma substation (Ref: 12/12/20/873) within the Ubuntu Local Municipality of the Pixley Ka Seme District Municipality, Northern Cape Province, approximately 39km from the town of Victoria West.

    Province(s): Northern Cape
    Author
    Arlene.Singh
    Last modified
    08/04/2025 - 11:08
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports Heritage & Palaeontological Impact Assessment reports Wouter Fourie, Elize Butler download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Final Comment Access Document