CaseDetails
Summary
Case ID
25130
Case Status
Proposal Description
Edison Solar PV (Pty) Ltd is proposing the development of the Edison Solar PV Energy Facility and associated infrastructure, located approximately 8km east of Durbanville within the City of Cape Town Municipality in the Western Cape Province. The development area is approximately 344ha on Portion 2 of the Farm Matjeskuil 733 and Portion 2 of the Farm Hercules Pilaar 1242.
The development includes a 150MW solar PV facility and 800MWh BESS . The electrical grid infrastructure (EGI) includes an on-site facility substation and a 66kV overhead line to connect the project to the Eskom grid at the existing 66kV Joostenberg Substation located immediately adjacent to the development area. The total line length is approximately 1km.
The infrastructure associated with the Edison Solar PV Energy will include:
• Solar PV arrays, modules, and mounting structures
• Inverters and transformers
• Cabling between the project components
• Battery Energy Storage System (BESS)
• On-site substation and switching substation
• 66kV OHL to connect to the Joostenberg Substation
• Site and internal access roads up to 10m in width, where required
• Temporary and permanent laydown areas, O&M buildings, security infrastructure, and fencing around the development area.
Table 1 below provides the details of the project, including the main infrastructure components and services that will be required during the project life cycle.
Table 1: Details of the Edison Solar PV Facility and associated infrastructure
Component Description / Dimensions
District Municipality
» City of Cape Town Metropolitan Municipality
Ward Number (s)
» Wards 102 and 105
Nearest town(s)
» 8km east of Durbanville
Farm name(s) and number(s) of properties affected by the PV Facility, including SG 21 Digit Code (s)
» Portion 2 of Farm Matjeskuil 733 (C05500000000073300002)
» Portion 2 of Farm Hercules Pilaar 1242 (C05500000000124200002)
Current zoning --- Agriculture
Site Coordinates (centre of development area)
» 33°47'52.71"S, 18°45'31.20"E
Total extent of the Development area --- ~344ha
Total extent of the Development footprint --- Estimated to be approximately 165ha for 150MW, but extent to be confirmed following specialist input during the scoping phase
Contracted capacity of the PV facility --- Up to 150MW
On-site Facility Substation and switching substation
» 66kV capacity
» Located within the development area.
» Up to 4ha in extent.
Overhead power line
» 66kV
» ~ 1km to connect to Joostenberg Substation (located on Portion 24 of Farm Joostenbergs Vlakte 724 (C05500000000072400024))
Battery Energy Storage System
» Capacity of 800MWh
» Up to up to 2ha in extent (adjacent to the On-site Facility Substation)
» 4m in height
Access roads and internal roads
» Existing roads will be used, wherever possible, to access the development area.
» Access 10m in width will be required
» Access roads approximately 2km in length
Other infrastructure
» Offices, workshop, operational control centre, operation and maintenance area, guard houses, ablution facilities
» Temporary and permanent laydown areas
» Security infrastructure
» Fencing around the development area.
» Parking facilities
The development includes a 150MW solar PV facility and 800MWh BESS . The electrical grid infrastructure (EGI) includes an on-site facility substation and a 66kV overhead line to connect the project to the Eskom grid at the existing 66kV Joostenberg Substation located immediately adjacent to the development area. The total line length is approximately 1km.
The infrastructure associated with the Edison Solar PV Energy will include:
• Solar PV arrays, modules, and mounting structures
• Inverters and transformers
• Cabling between the project components
• Battery Energy Storage System (BESS)
• On-site substation and switching substation
• 66kV OHL to connect to the Joostenberg Substation
• Site and internal access roads up to 10m in width, where required
• Temporary and permanent laydown areas, O&M buildings, security infrastructure, and fencing around the development area.
Table 1 below provides the details of the project, including the main infrastructure components and services that will be required during the project life cycle.
Table 1: Details of the Edison Solar PV Facility and associated infrastructure
Component Description / Dimensions
District Municipality
» City of Cape Town Metropolitan Municipality
Ward Number (s)
» Wards 102 and 105
Nearest town(s)
» 8km east of Durbanville
Farm name(s) and number(s) of properties affected by the PV Facility, including SG 21 Digit Code (s)
» Portion 2 of Farm Matjeskuil 733 (C05500000000073300002)
» Portion 2 of Farm Hercules Pilaar 1242 (C05500000000124200002)
Current zoning --- Agriculture
Site Coordinates (centre of development area)
» 33°47'52.71"S, 18°45'31.20"E
Total extent of the Development area --- ~344ha
Total extent of the Development footprint --- Estimated to be approximately 165ha for 150MW, but extent to be confirmed following specialist input during the scoping phase
Contracted capacity of the PV facility --- Up to 150MW
On-site Facility Substation and switching substation
» 66kV capacity
» Located within the development area.
» Up to 4ha in extent.
Overhead power line
» 66kV
» ~ 1km to connect to Joostenberg Substation (located on Portion 24 of Farm Joostenbergs Vlakte 724 (C05500000000072400024))
Battery Energy Storage System
» Capacity of 800MWh
» Up to up to 2ha in extent (adjacent to the On-site Facility Substation)
» 4m in height
Access roads and internal roads
» Existing roads will be used, wherever possible, to access the development area.
» Access 10m in width will be required
» Access roads approximately 2km in length
Other infrastructure
» Offices, workshop, operational control centre, operation and maintenance area, guard houses, ablution facilities
» Temporary and permanent laydown areas
» Security infrastructure
» Fencing around the development area.
» Parking facilities