CaseDetails
    Summary
    Case ID
    8532
    Case Status
    Heritage Authority(s)
    LIHRA
    Official Reference

    9247

    Proposal Description
    It is proposed that the two existing, damaged low-water bridges on Portion 1 of the farm St. George 2-JT near Gamawela Village be upgraded. Parts of the existing crossings were destroyed by floods in 2010, and during times of heavy flow in the Klein Dwars River and its tributaries, the crossings become impassable to local community members.
    Author
    louise.agenbag
    Last modified
    23/10/2023 - 17:49
    Reports
    Heritage Reports linked to this Case
    Heritage Impact Assessment Specialist Reports Phase 1 Heritage Resource Impact Assessment (Scoping & Evaluation) PROPOSED UPGRADING OF EXISTING LOW-LEVEL BRIDGE GA-MAWELA VILLAGE, STEELPOORT, LIMPOPO Liesl Stegmann download
    Official
    Case Officers
      Location
      Location
      Decisions, Comments + Permits
      Decision Date Type
      Interim Comment Access Document