Exxaro submitted a MRA for the Belfast Project in accordance with requirements contained in the MPRDA. The DMR awarded a mining right for the Belfast Project in 2015. Exxaro also applied for Environmental Authorisation in terms of the NEMA to the MDEDET, who granted authorisation on 4 July 2013. The development affected 32 households and around 200 graves.
SAHRA issued permits to exhume and relocate around 160 graves. The grave relocations were completed in October 2019. Sibsequently, an unknown grave was discovered in close proximity to the current open pit mine. the SAHRA BGG required that this grave be relocated as a 100 m buffer cannot be maintained.
SAHRA issued permits to exhume and relocate around 160 graves. The grave relocations were completed in October 2019. Sibsequently, an unknown grave was discovered in close proximity to the current open pit mine. the SAHRA BGG required that this grave be relocated as a 100 m buffer cannot be maintained.
Inventory Reference
Post date
06/04/2016 - 11:38
Last modified
23/10/2023 - 17:49
Reports
Burial Grounds and Graves Specialist Reports | EXX3775_Belfast_GRP_Report_Addendum | Justin du Piesanie | download | |
Burial Grounds and Graves Specialist Reports | EXX3775_Belfast_Interim_GRP_Report | Justin du Piesanie | ||
Burial Grounds and Graves Specialist Reports | EXX6685 Site Inspection Report | Justin du Piesanie | download | |
BGG Phase 2 | EXX6885_Belfast_GRP_Close-Out_Report | Muofhe Ravhura, Johan Nel | download | |
BGG Phase 2 | Exxaro Belfast Coal Mine Section 36 Permit Application Report | Johan Nel | download | |
BGG Phase 1 | Exxaro_Belfast_BGGC_report | Johan Nel | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document | |
Permit | Access Document | |
Permit | Access Document | |
Permit | Access Document | |
Permit | Access Document |