CaseReference
Applicable legislation
36(3)
Decision Date
Committee
Decision Status
Case Decision

Final Decision
SAHRA Burial Grounds and Graves unit (BGG) acknowledges receipt of the submitted inspection report. However, we reject the in-situ conservation recommended by the Heritage Specialist for the following reasons:

The proposed 15 m buffer-zone is unreasonably less than the required 100m for mining operations.
In-situ preservation cannot be authorized with such high potential for the grave to be damaged.  

As it is seemingly impossible to meet the required 100m buffer-zone, it is recommended that Grave-Exhumation and relocation Process which includes a FULL 60 days public consultation be initiated for the grave to be exhumed and relocated to a local municipal cemetery specified during consultations. Please let us know when an exhumation application is lodged.