CaseDetails
Summary
Case ID
16438
Case Status
Proposal Description
Eskom is intending to construct a 22kV powerline that will be 10 695 km in length. The powerline will begin at the Gamohaan Substation and will electrify the community of Seokama. The proposed powerline is situated in the Ga-Segonyane local Municipality, near Kuruman, Northern Cape.
Post date
25/11/2021 - 14:07
Last modified
21/10/2023 - 13:22
Reports
Heritage Impact Assessment Specialist Reports | Heritage Impact Assessment: Gamohaan Seokama 22kV powerline | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document | |
Response to NID (Notification of Intent to Develop) | Access Document |