Proposal Description
Proposed 22kV power line from Reitz munic substation to Petsana exyension 2. Power line to be constructed with wooden pole structures that goes maximum 1.8 meters into the ground. The power line to be stringed with hare conductor. The power is to take off from an existing power line in the substation vicinity and aligned along existing power lines. Reitz, Nketoana local municipality, Free State province
Post date
04/01/2022 - 11:01
Last modified
21/10/2023 - 13:22
Reports
Archaeological Monitoring | ReitzPetsana: Burial Ground demarcation report | Alvord Nhundu | download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Decision | Access Document | |
Interim Comment | Access Document |