Proposal Description
The applicant proposes to develop a 66kV overhead powerline from the Safariland substation to the Bien Donne substation in the Southern Paarl/Simondium region. The powerline will run for nearly 7km from north near the R301 to the R45 in the south. The powerline will have a capacity of 66kV and service the most northern portion of the Stellenbosch Municipality near Simonsberg in Groot Drakenstein.
Inventory Reference
Post date
07/08/2023 - 13:26
Last modified
21/10/2023 - 13:43
Reports
HIA Phase 1 | HIA: Bien Donne Grid | Jenna Lavin | download |
Official Use
Official
Case Officers
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Interim Comment | Access Document |